East Isles Sewer Improvements Project

ES Project No. 804125

Text Alert Icons Project Alert

Project Update: April 29, 2025 - updated map and timeline.  See Project Updates below.

To receive project updates via email or text, sign up using the E-newsletter/SMS subscription form on the right.

 

Project Description

Metropolitan Council Environmental Services (ES), operator of the metro area wastewater collection and treatment system, is replacing and enlarging the aging regional sanitary sewer pipe and structures near Lake of the Isles.

Improvements to the regional sanitary sewer system along The Mall road are being completed in coordination with the Minneapolis Park and Recreation Board’s (MPRB) planned improvements for The Mall determined as part of a long-term park planning effort completed in 2020

Improvements to the regional sanitary sewer system along Humboldt Avenue and the City of Minneapolis’ utility work were completed in 2022.

The Mall (tentatively 2026)

We are replacing the existing sanitary sewer pipes along The Mall between Bda Maka Ska Parkway and Humboldt Avenue with new and larger pipes. We anticipate construction will begin spring 2026 and completed in late summer 2026. Final restoration activities may continue through fall 2027.

The Minneapolis Park and Recreation Board (MPRB) decided not to construct the Woonerf in conjunction with our sewer improvements project. ES will restore The Mall road as directed by MPRB.

  • Visit MPRB’s project website for more information on the Southwest Service Area Master Plan and to sign up for their email updates to stay informed about their upcoming community meetings.

Project area maps

 

Map showing the sanitary sewer pipe along the west bound lanes of The Mall between Bde Maka Ska Parkway East and Humboldt Avenue South.

 

Schedule

 

Schedule graphic showing engagement and design will occur from Fall 2023 through spring 2024. Construction will occur fom summer 2024 through winter 2024. Final restoration will continue from spring 2025 through summer 2025.


Project Updates

Project Update - December 20, 2023 (PDF) 212 kB

Project Update - November 3, 2023 (PDF) 421 kB

Project Staff

 

Project Manager: Chad Davison, Principal Engineer, Interceptor Engineering
Council's Authorized Representative: Kim Sanders, Principal Contract Administrator, Construction Services
 

Project Contact

For information, please contact:

Email: info@eastislessewerproject.com
Phone: 612-439-5225  

Sign up for E-newsletter/SMS at the top right of the page.