Traffic Impact
Expect Miami Foley Road to have a single lane open with a temporary traffic signal helping guide traffic along with construction noise and delays. On June 5, expect Miami Foley Road to temporarily close completely between 7 a.m. to 5 p.m. We plan to reopen the road the same day. Detour around the closure using U.S. 101.
Construction Impacts
During construction, you can expect:
Crews working during the day.
A single lane open with a temporary traffic signal helping guide traffic.
Construction noise and delays.
A total of four full road closures, two at Dry Creek and two at Crystal Creek.
On Thursday, June 5, we're temporarily closing Miami Foley Road as we continue to replace the existing Dry Creek culvert with a new bridge. During the June 5 closure, you can expect:
Miami Foley Road to close on both sides of Dry Creek from 7 a.m. to 5 p.m.
To detour around the closure using U.S. 101.
Crews working during the day.
Construction noise and delays.
We plan to reopen a single lane of Miami Foley Road by 5 p.m. the same day, June 5.
Sign up for project emails to get updates about when the next two closures at Crystal Creek will start and other impacts! We'll share more information as soon as we know the schedule.
Construction Activities
We're building two new bridges over Dry Creek and Crystal Creek.
On Thursday, June 5, we're temporarily closing Miami Foley Road so we can bring in a large crane at Dry Creek. We plan to reopen the road later the same day by 5 p.m.
Visit TripCheck for the most current traffic information.
Pedestrians, including those with disabilities, will have access through or around work zones.
Pay attention in the work zone, slow down and move over – imagine this is where you work!
Always drive safely, watch for construction signs and workers.
Remember: fines double in all Oregon work zones, whether workers and signs are present or not.